Electrical Requirements:
220-240 V AC, 50 Hz (Dubai standard), fixed 16A-32A circuit, minimum 2.5 mm² wire gauge, grounding compulsory, GFCI protection on bathrooms.
🔥
Gas Specifications:
Natural gas/LPG compatible, 20-25 mbar pressure (natural gas), minimum 15mm pipe, CO detector suggested, minimum 200 cm² ventilation opening.
💧
Plumbing Connections:
2-4 bar optimum water pressure, copper/PEX/CPVC pipes 95°C minimum, inlet/outlet isolation valves, closed system expansion tank, drain valve, service.
🛡️
Safety Features:
TPR valve (150 kPa/99°C tested), visible drain pipe that is routed out, stability seismic straps, and catch pan used when installed indoors.
📏
Installation Standards:
50cm clearance allowance to access service, wall unit 1.5-1.8m high, well-ventilated, floor drainage in 2m, and wall bracket with a 3x unit weight rating.
⚙️
Testing and Commissioning:
During the pre-completion phase, we perform pressure tests, temperature tests, gas leak tests (in the case of gas units), electric safety tests, and flow rate tests to ensure correct operation.